Work still continues on the new scoreboard and storage facility with the brick work now completed and rendered. The fixing of the roof is scheduled for Friday, and installation of the electronic scoreboard is planned for this coming Monday.
Prior to the scoreboard being installed, the steel framework needs to be painted. If there are any painters in the club that would be able to assist please call Damian Pearce on 0411 554 509.
All going well we will be able to showcase the new electronic scoreboard when hosting the Under 12 finals on August 10.
Last Modified on 23/07/2014 13:33