Update on
Holm Park Rd Development
The new ground is progressing with the major earth works well underway. At the time of going to press the drainage will be completed and the irrigation installed on both ovals, to be followed by the sand and soil top layer. The entrance driveway will also be commenced this week.
The club sub committee headed by Gary Valentine is workingclosely with Council and their architect to finalise the design of the club rooms. Due to Council budget constraints the design of the facilities will involve two stages.
Stage one will be the Council funded lower level incorporating change rooms, showers, toilets, trainers rooms, store rooms, canteen and office.
Stage two is being designed with the upper story being the 200 seat social room , bar, cool room, toilets and kitchen..
The funding of this stage may have to be a joint venture between Council and the BFC over the next few years.